Skip to content. Skip to navigation

CINEFOGO Network of Excellence

Sections
You are here: Home
Document Actions

Project management & reporting

Project legal, financial and management fundamentals - contract, consortium agreement, reports & reporting guidelines...

How to communicate with project management office at Roskilde University

  • All e-mail communication related to CINEFOGO should be sent exclusively to cinefogo@ruc.dk.
  • Please indicate work package number (WPxx) or contractor number (CRxx) in e-mail subject where possible.

Contractual documents

Contract CIT3-CT-2005-513350Scanned document including all signed "Forms A" (Accession to the Contract) and later added "Forms B" (Request for accession of a new contractor to the Contract)
Consortium AgreementVersion from June 2005 (recovered), including scanned signed pages
Annex I to the Contract"Technical Annex" including original appendices A-E and also appendices F-K added later by contract amendments
Annex II to the Contract"General Conditions"
Annex III to the Contract"Networks of Excellence"

Amendment No. 1 to the Contract

Date: 29-03-2006
- Removal of contractor no. 4 due to non-accession to the Consortium
- Accession of contractor no. 49 to the Contract
- Addition of Special clause 32 regarding submission of Audit certificates

Amendment No. 2 to the Contract

Date: 19-12-2007
- Addition of contractors no. 50, 51, 52 and 55
- Termination of participation of contractors no. 6, 9 and 40
- Addition of special clauses 22 and 23
Incomplete documentation for this amendment was completed by a "Document supplement", sent to the EC on 8th of August 2008.
"Information letter no. 1" - not found
Amendment No. 3 does not exist. EC internal database indicates a document called "Information letter no. 1" under this entry. Original document was not found in CINEFOGO office. The letter clarified some changes related to contractor No. 27 (SCP).

Amendment No. 4 to the Contract

 Date: 08-04-2009
- Addition of contractors no. 53 and 54
Change of coordinator's name
Date: 20-04-2009
- Letter informing about change of Danish name of Roskilde University - new Danish name is Roskilde Universitet
- English name remains unchanged, Roskilde University

Amendment No. 5 to the Contract

Date: 08-07-2009
- Modification of project duration (extension by 3 months)
- Modification of the reporting periods (compromise solution incorporating causeless change of months' and periods' numbers taking place in 2006 and 2007)

Project reports

Period
---
Months
Activity reports
WP perspective, how goals were reached
Management reports
Contractors' perspective, how money were spent
Review reports
Evaluation of project performance
P1
---
1-12
Activity report 2005-2006 - covering September 2005 - August 2006. The report temporarily changed months numbering from 1-48 to 0-47. This causeless change violating several Articles of the Contract had to be legalized. This causeless change violating several Articles of the Contract had to be settled, therefore in May 2009, numbering of months was put back to 1-48. Numbering of periods also was also put back to 1-4.Management report 2005-2006 - covering September 2005 - August 2006Review report 2005-2006 - reviewing and evaluating project performance based on Activity report 2005-2006, Management report 2005-2006 and documentation available on project portal www.cinefogo.org
P2
---
13-24

Activity report 2006-2007 - covering September 2006 - August 2007Complete overview of use of financial resources in relation to second yearly Activity reports composed of two reports.
"Interim" management report was a report initiated by then secretariat, covering September 2006 - February or March 2007. No Activity report was submitted at this time. The report was made because of misunderstanding of project years and 18-months planning periods - the misconception presented as "overlapping periods". The report temporarily changed period numbering (project periods corresponding to project years) from 1-4 to 1-5, where original year 2 (period 2) became period 2+3. This causeless change violating several Articles of the Contract had to be settled, therefore in May 2009, numbering of months was put back to 1-48. Numbering of periods also was also put back to 1-4.
Management report 2007 - covering April 2007 - August 2007. This report was submitted together with the second yearly Activity report.
Review report 2006-2007 - reviewing and evaluating project performance based on Activity report 2006-2007, Management report 2006-2007 and documentation available on project portal and through available on-line resources
P3
---
25-36
Activity report 2007-2008 - covering September 2007 - August 2008Management report 2007-2008 - covering September 2007 - August 2008Review report 2007-2008 - reviewing and evaluating project performance based on Activity report 2007-2008, Management report 2007-2008 and documentation available on project portal and through available on-line resources
P4
---
37-51
Activity report 2008-2009 - covering September 2008 - November 2009 Management report 2008-2009 - covering September 2008 - November 2009 Final review


How to communicate with project management office at Roskilde University

  • All e-mail communication related to CINEFOGO should be sent exclusively to cinefogo@ruc.dk.
  • Please indicate work package number (WPxx) or contractor number (CRxx) in e-mail subject where possible.

Headquartered at the University of Roskilde Run under the EU's Sixth Framework Programme Funded by the European Union

Copyright © 2005-2008 CINEFOGO